Municipality of Midsalip

Province of Zamboanga del Sur

Municipal Planning and Development Office

MEO Project Status

Fiscal Year 2026
BarangayProjectsABCDisbursedAvg Physical %
Camalan1₱3,400,000.00₱2,815,000.0088%
El Salvador1₱8,000,000.00₱942,000.0012%
Lala Proper2₱3,000,000.00₱1,230,000.0065%
Magpatao1₱1,250,000.00₱0.000%
Maranding1₱5,000,000.00₱2,945,000.0062%
Fund SourceProjectsABCDisbursed
20% Development Fund1₱2,300,000.00₱545,000.00
General Fund (GF)3₱6,950,000.00₱3,630,000.00
LDRRMF Capital2₱11,400,000.00₱3,757,000.00
CodeTitleBarangayContractorStatusPhys %Fin %ABCDisbursed
MEO-2026-0001Maranding Road ConcretingMarandingLanao Construction & Supply Corp.Ongoing62%58%₱5,000,000.00₱2,945,000.00
MEO-2026-0002Lala Proper Drainage CanalLala ProperOngoing30%25%₱2,300,000.00₱545,000.00
MEO-2026-0003Camalan Multi-Purpose BuildingCamalanCamalan Construction ServicesSubstantially Completed88%88%₱3,400,000.00₱2,815,000.00
MEO-2026-0004El Salvador Evacuation CenterEl SalvadorIligan Engineering Corp.Ongoing12%12%₱8,000,000.00₱942,000.00
MEO-2026-0005Magpatao Footbridge RepairMagpataoFor Procurement0%0%₱1,250,000.00₱0.00
MEO-2026-0006Brgy Hall Roofing — Lala ProperLala ProperTBL Roofing SpecialistsCompleted100%100%₱700,000.00₱685,000.00
Prepared by:
MPDC Staff
Planning Officer
Reviewed by:
MPDC Coordinator