| Barangay | Projects | ABC | Disbursed | Avg Physical % |
|---|---|---|---|---|
| Camalan | 1 | ₱3,400,000.00 | ₱2,815,000.00 | 88% |
| El Salvador | 1 | ₱8,000,000.00 | ₱942,000.00 | 12% |
| Lala Proper | 2 | ₱3,000,000.00 | ₱1,230,000.00 | 65% |
| Magpatao | 1 | ₱1,250,000.00 | ₱0.00 | 0% |
| Maranding | 1 | ₱5,000,000.00 | ₱2,945,000.00 | 62% |
| Fund Source | Projects | ABC | Disbursed |
|---|---|---|---|
| 20% Development Fund | 1 | ₱2,300,000.00 | ₱545,000.00 |
| General Fund (GF) | 3 | ₱6,950,000.00 | ₱3,630,000.00 |
| LDRRMF Capital | 2 | ₱11,400,000.00 | ₱3,757,000.00 |
| Code | Title | Barangay | Contractor | Status | Phys % | Fin % | ABC | Disbursed |
|---|---|---|---|---|---|---|---|---|
| MEO-2026-0001 | Maranding Road Concreting | Maranding | Lanao Construction & Supply Corp. | Ongoing | 62% | 58% | ₱5,000,000.00 | ₱2,945,000.00 |
| MEO-2026-0002 | Lala Proper Drainage Canal | Lala Proper | Ongoing | 30% | 25% | ₱2,300,000.00 | ₱545,000.00 | |
| MEO-2026-0003 | Camalan Multi-Purpose Building | Camalan | Camalan Construction Services | Substantially Completed | 88% | 88% | ₱3,400,000.00 | ₱2,815,000.00 |
| MEO-2026-0004 | El Salvador Evacuation Center | El Salvador | Iligan Engineering Corp. | Ongoing | 12% | 12% | ₱8,000,000.00 | ₱942,000.00 |
| MEO-2026-0005 | Magpatao Footbridge Repair | Magpatao | For Procurement | 0% | 0% | ₱1,250,000.00 | ₱0.00 | |
| MEO-2026-0006 | Brgy Hall Roofing — Lala Proper | Lala Proper | TBL Roofing Specialists | Completed | 100% | 100% | ₱700,000.00 | ₱685,000.00 |