Municipal Engineer’s Office · FY 2026

Status & Reports

Engineering project status, per-barangay and per-fund roll-ups. The Engineer’s Office owns these records — add, edit, or close out projects here. MPDC sees a read-only copy for planning.

Excel PDF

Per-Barangay Accomplishment Excel

BarangayProjectsABCDisbursedAvg Phys %
Camalan1 ₱3,400,000.00₱2,815,000.00 88%
El Salvador1 ₱8,000,000.00₱942,000.00 12%
Lala Proper2 ₱3,000,000.00₱1,230,000.00 65%
Magpatao1 ₱1,250,000.00₱0.00 0%
Maranding1 ₱5,000,000.00₱2,945,000.00 62%

Per-Fund Roll-up Excel

Fund SourceProjectsABCDisbursed
20% Development Fund1 ₱2,300,000.00₱545,000.00
General Fund (GF)3 ₱6,950,000.00₱3,630,000.00
LDRRMF Capital2 ₱11,400,000.00₱3,757,000.00

Project Status 6 projects · ABC ₱20,650,000.00 · Disbursed ₱7,932,000.00

CodeTitleBarangayContractorStatusPhys %Fin %ABCDisbursedActions
MEO-2026-0001 Maranding Road Concreting Maranding Lanao Construction & Supply Corp. Ongoing
62%
58% ₱5,000,000.00 ₱2,945,000.00
MEO-2026-0002 Lala Proper Drainage Canal Lala Proper Ongoing
30%
25% ₱2,300,000.00 ₱545,000.00
MEO-2026-0003 Camalan Multi-Purpose Building Camalan Camalan Construction Services Substantially Completed
88%
88% ₱3,400,000.00 ₱2,815,000.00
MEO-2026-0004 El Salvador Evacuation Center El Salvador Iligan Engineering Corp. Ongoing
12%
12% ₱8,000,000.00 ₱942,000.00
MEO-2026-0005 Magpatao Footbridge Repair Magpatao For Procurement
0%
0% ₱1,250,000.00 ₱0.00
MEO-2026-0006 Brgy Hall Roofing — Lala Proper Lala Proper TBL Roofing Specialists Completed
100%
100% ₱700,000.00 ₱685,000.00

Click any row to open the full project. Edits flow automatically to the MPDC “MEO Project Status” report.

MIDSALIP LGU, ZDS © 2026 Municipality of Midsalip, Zamboanga del Sur
Budget, Accounting & Treasury Integrated System v1.0.0
Loading...
Notifications & Queue Alerts
Loading...
DBATIS LIVE
Loading notifications...